Gantt charts are useful for showing a project plan, a publication timeline, or any other schedule organized along a numeric time axis. tikzfigure provides a small structured wrapper around LaTeX’s pgfgantt package.

The package is added automatically when you create a chart, so the same figure can be exported with generate_standalone() or compiled with show().

from tikzfigure import TikzFigure

Pass the first and last time slot to gantt() and describe rows with small dictionaries. The supported row types are title, titlelist, group, bar, milestone, link, and raw.

fig = TikzFigure()
fig.gantt(
1,
12,
options=["hgrid", "vgrid"],
rows=[
{"type": "titlelist", "content": "1,2,3,4,5,6,7,8,9,10,11,12"},
{"type": "group", "content": "Discovery", "start": 1, "end": 3},
{"type": "bar", "content": "Research", "start": 1, "end": 2},
{"type": "bar", "content": "Requirements", "start": 2, "end": 3},
{"type": "group", "content": "Delivery", "start": 4, "end": 12},
{"type": "bar", "content": "Implementation", "start": 4, "end": 8},
{"type": "bar", "content": "Testing", "start": 8, "end": 10},
{"type": "milestone", "content": "Release", "at": 12},
],
)
print(fig.generate_tikz())
% --------------------------------------------- %
% Tikzfigure generated by tikzfigure v0.5.0 %
% https://github.com/max-models/tikzfigure %
% --------------------------------------------- %
\begin{tikzpicture}
\begin{ganttchart}[hgrid, vgrid]{1}{12}
\gantttitlelist{1,2,3,4,5,6,7,8,9,10,11,12}{1}\\
\ganttgroup{Discovery}{1}{3}\\
\ganttbar{Research}{1}{2}\\
\ganttbar{Requirements}{2}{3}\\
\ganttgroup{Delivery}{4}{12}\\
\ganttbar{Implementation}{4}{8}\\
\ganttbar{Testing}{8}{10}\\
\ganttmilestone{Release}{12}\\
\end{ganttchart}
\end{tikzpicture}

Call fig.show() in a notebook to compile and display the chart, or save it with fig.savefig("project-plan.pdf").

Give bars and milestones a name and connect them with link rows. The names are passed to pgfgantt and are used by ganttlink.

fig = TikzFigure()
chart = fig.add_gantt_chart(
1,
8,
options=["hgrid", "vgrid"],
)
chart.add_row(
"titlelist",
content="Jan,Feb,Mar,Apr,May,Jun,Jul,Aug",
width=1,
# Text labels must not be run through pgfmath's default numeric
# evaluation, which pgfgantt otherwise applies to titlelist entries.
options=[r"title list options={var=\x}"],
)
chart.add_row(
"bar",
content="Design",
start=1,
end=3,
name="design",
options=["progress=100"],
)
chart.add_row(
"bar",
content="Build",
start=3,
end=6,
name="build",
options=["progress=60"],
)
chart.add_row("milestone", content="Launch", at=8, name="launch")
chart.add_row("link", source="design", target="build")
chart.add_row("link", source="build", target="launch")
fig.show()
/home/runner/work/tikzfigure/tikzfigure/.venv/lib/python3.12/site-packages/fitz/__init__.py:17: FutureWarning: The `fitz` API is deprecated and will be removed in future. Use `import pymupdf` instead.
warnings.warn(
Notebook output

add_gantt_chart() is the explicit spelling; gantt() and add_gantt() are short aliases. The returned GanttChart can be extended incrementally with add_row(), which is convenient when rows come from application data.

This example mirrors a common plotting API: task names, starts, and durations are kept in parallel Python lists. Convert each phase into Gantt rows and use per-bar options to give the phases distinct colors.

phase1_tasks = ["Requirements", "Architecture", "UI Design"]
phase1_starts = [0, 3, 6]
phase1_durations = [3, 3, 4]
phase2_tasks = ["Backend Dev", "Frontend Dev", "Integration"]
phase2_starts = [10, 10, 20]
phase2_durations = [10, 10, 5]
phase3_tasks = ["Unit Tests", "Integration Tests", "UAT"]
phase3_starts = [25, 28, 32]
phase3_durations = [3, 4, 3]
def phase_rows(title, tasks, starts, durations, fill, draw):
rows = [
{
"type": "group",
"content": title,
"start": min(starts),
"end": max(start + duration for start, duration in zip(starts, durations)),
}
]
rows.extend(
{
"type": "bar",
"content": task,
"start": start,
"end": start + duration,
# pgfgantt bars are styled via the `bar` style itself, not raw
# `fill=`/`draw=` keys (those live outside the /pgfgantt family).
"options": [f"bar/.append style={{fill={fill}, draw={draw}}}"],
}
for task, start, duration in zip(tasks, starts, durations)
)
return rows
rows = [{"type": "titlelist", "content": ",".join(str(i) for i in range(36))}]
rows += phase_rows(
"Planning", phase1_tasks, phase1_starts, phase1_durations, "LightBlue", "blue"
)
rows += phase_rows(
"Development", phase2_tasks, phase2_starts, phase2_durations, "LightGreen", "green"
)
rows += phase_rows(
"Testing", phase3_tasks, phase3_starts, phase3_durations, "LightYellow", "orange"
)
fig = TikzFigure()
fig.gantt(0, 35, rows=rows, options=["hgrid", "vgrid", "bar height=.6"])
fig.show()
Notebook output

The same row-building pattern works when each row represents a person rather than a project phase.

team_members = ["Alice", "Bob", "Charlie", "Diana", "Eve"]
task_starts = [0, 5, 3, 8, 10]
task_durations = [8, 6, 10, 7, 5]
team_rows = [{"type": "titlelist", "content": ",".join(str(i) for i in range(19))}]
team_rows.extend(
{
"type": "bar",
"content": member,
"start": start,
"end": start + duration,
"options": ["bar/.append style={fill=Coral, draw=DarkRed, fill opacity=.7}"],
}
for member, start, duration in zip(team_members, task_starts, task_durations)
)
fig = TikzFigure()
fig.gantt(0, 18, rows=team_rows, options=["hgrid", "vgrid"])
fig.show()
Notebook output

Rows are ordinary dictionaries, so they can be generated from CSV files, database records, or any other application data. Use a raw row when a pgfgantt command is not covered by the structured row types.